• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2023 - May 2024
  • Estimated project cost $779,744
  • Australian Government contribution $590,978
  • Local Council/Shire Huon Valley Council
  • State TAS

Project description

This is the next stage of a multi-staged work program for Esperance Coast Road. This road is the main Council owned Distributor Road linking Geeveston to Dover. Additional allocation was used for next stage of the project from chainage 15579 and 19009.

Mill and repair failures to depth of 100 millimeters, resurface 2120m and 3430m, total of 5550m with a single coat reseal and 500 millimeter gravel shoulders. Cleanout drains, install guideposts, signage and reinstate line marking.

Total cost of proposed project is $779,744

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.