• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2023 - Jan 2024
  • Estimated project cost $226,651
  • Australian Government contribution $226,651
  • State NSW

Project description

Pavement and seal failure & washout due to storm & flooding events.

Reconstruction of 1.1km of pavement and seal with 10m formation and 8m seal. Rip, stabilise, shape and compact existing 150mm pavement to reform subgrade. Construct new 200mm pavement in 2 layers, compact, trim and seal with 14/7 wearing course.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.