• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2024 - May 2024
  • Estimated project cost $325,600
  • Australian Government contribution $189,448
  • State NSW

Project description

Quarry Road pavement has extensive failure approximately 80% of the area. Pavement length is 340m and average width is 8m. Kerb and gutter has failed for approximately 10% of the length.

Rehabilitation of the pavement by heavy patching, profiling and resurfacing. Replacement of failed kerb and gutter.

Total cost of proposed project is $325,600

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.