• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2024 - Jun 2024
  • Estimated project cost $277,689
  • Australian Government contribution $74,772
  • Local Council/Shire Junee Shire Council
  • State NSW

Project description

Narrow Road and poor alignment posses significant safety risks. Pavement damage including shoves, bleeding and potholes are additional safety concerns. Project rectifies these issues.

The project includes widening to 7m seal minimum, reshaping table drain, traffic control, lime stabilisation of sub-base to a depth of 200mm, addition of 150mm of thick base layer comprising of DGS/DGB material and a 14mm/7mm double coat sealed wearing course.

Total cost of proposed project is $277,689

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.