• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Apr 2024 - Jun 2024
  • Estimated project cost $294,603
  • Australian Government contribution $147,598
  • Local Council/Shire Shire of Capel
  • State WA

Project description

Road deterioration of existing bitumen seal and edge. The road is too narrow for an urban environment and the terminating end of road (Goodwood Road) does not provide adequate turn around for large vehicles e.g. waste trucks.

The road will be widened from 5.5m to 6.0m to meet minimum criteria in accordance with livable neighbourhood standards and a cul-de-sac head will be provided at the terminating end near Goodwood Road. Design and Rehabilitation (Asphalt).

Total cost of proposed project is $294,603

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.