• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2024 - Apr 2024
  • Estimated project cost $111,182
  • Australian Government contribution $111,182
  • Local Council/Shire Shire of Nannup
  • State WA

Project description

Repair a V-drain that has badly scoured during winter rains. Parts of the shoulder have given way. The backslope batter is too steep. Requires major works.

Excavate scoured section. Import stone to rock pitch. Improve slope of large backslope batter. Install concrete spoon drain.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.