• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2024 - Jun 2024
  • Estimated project cost $90,000
  • Australian Government contribution $70,000
  • Local Council/Shire City of Mandurah
  • State WA

Project description

Littleton Street was assessed during the 2020 road network visual condition assessment and given an overall Visual Condition Rating (VCR) of 5. The existing surface is heavily cracked and patch work at various intersections.

Resurfacing of Littleton Street with a Single Single seal using S45R • Total area 6900m2 • Heavy Patching approx. 60m2

Total cost of proposed project is $90,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.