• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2024 - Apr 2024
  • Estimated project cost $41,965
  • Australian Government contribution $41,965
  • Local Council/Shire Hay Shire Council
  • State NSW

Project description

Aged bitumen has deteriorated forming cracks and potholes creating safety risks for road users.

Heavy patching of the following areas: Patch 1 - 60m2 at Corner Moppett & Pine Streets (South side) $4,410.00, Patch 2 - 62m2 at Corner Moppett & Pine Streets (North side) $4,557.00, Patch 3 - 114m2 at Corner Morgan & Pine Streets (North side) $8,379.00, Patch 4 - 135m2 at 200 Pine Street (HWMHS bus stop) $8,928.00, Patch 5 - 83m2 Balaclava St (East end near cross street of Edward St, Hay), Patch 6 - 27m2 Balaclava St (West end near cross street of Lachlan Street, Hay) $1,984.50, Patch 7 - 117m2 at Corner Edward & Leonard Streets (whole south side) $7,607.00

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.