• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2022 - Jun 2023
  • Estimated project cost $180,320
  • Australian Government contribution $176,294
  • Local Council/Shire Alexandrina Council
  • State SA

Project description

The road surface condition has reached the intervention point for renewal. Problems being addressed Include: surface breakthrough, shape loss, pot holes and patching.

The repairs to the identified surface defects and reseal, with 14/7 Spray Seal, have restored the roads surface to a safe condition. Includes Line Marking. A total Length of 2.49 Km

Total cost of proposed project is $180,320

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.