• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2024 - Jun 2024
  • Estimated project cost $74,822
  • Australian Government contribution $70,000
  • Local Council/Shire Redland City Council
  • State QLD

Project description

A condition assessment has determined that the bridge on Boundary Street requires impermeable membrane installation to extend its useful life.

Remove Asphalt over bridge deck sand blast concrete deck before installing waterproofing membrane (seal with S25E polymer modified binder then 75mm AC14H with A15E polymer modified binder surface course with 25mm SMA7 A15E

Total cost of proposed project is $74,822

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.