• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2025 - Sep 2025
  • Estimated project cost $416,411
  • Australian Government contribution $416,411
  • State NT

Project description

The current road seal is poor and stripping and cracking badly.

Reseal 5.08 km of road as per current standard.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.