• Funding program Roads to Recovery Program
  • Status Under construction
  • Transport mode Road
  • Expected start/finish Jul 2025 - Jun 2026
  • Estimated project cost $39,974
  • Australian Government contribution $39,974
  • Local Council/Shire Port Macquarie Hastings Council
  • State NSW

Project description

The existing thin asphalt layer is deteriorating and unsuitable for milling. A surface treatment is needed to restore condition without compromising underlying gravel layers.

Apply microsurfacing or slurry seal, avoiding milling into gravel. The existing asphalt concrete (AC) is a maximum of 40 mm thick. Apply a 10 mm S45R seal followed by a 7 mm rack coat.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.