• Funding program Roads to Recovery Program
  • Status Under construction
  • Transport mode Road
  • Expected start/finish Nov 2025 - Feb 2026
  • Estimated project cost $302,925
  • Australian Government contribution $302,925
  • Local Council/Shire Campbelltown City Council
  • State NSW

Project description

The road is heavily affected by significant levels of crocodile cracking & rutting.

The proposed treatment includes in-situ cement stabilisation followed by hot mix asphalt with interlayer seal. The total area of proposed treatment is 4039 m2, Length is 622 m, Width is 6.5 m.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.