• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2025 - Aug 2025
  • Estimated project cost $42,509
  • Australian Government contribution $42,509
  • Local Council/Shire Willoughby City Council
  • State NSW

Project description

Existing pavement has deteriorated. Cracks have developed along the road pavement with the surface stone stripping, requiring resurfacing.

Surface area of 96 x 7.1 m to be removed and replaced with 70 mm AC14 asphalt. Approximately 60 sqm heavy patching.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.