• Funding program Roads to Recovery Program
  • Status Underway
  • Transport mode Road
  • Expected start/finish Jul 2025 - Oct 2025
  • Estimated project cost $412,055
  • Australian Government contribution $412,055
  • State NSW

Project description

Road pavement is showing distress and there are severe cracking/damaged including pothole patched over time. Trees have damaged a section of kerb & gutter. Pavement damages will need to be addressed prior to resurfacing. Reconstruction of pavement with100mm AC14 and resurface with 50mm AC10.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.