• Funding program Roads to Recovery Program
  • Status In planning
  • Transport mode Road
  • Expected start/finish Aug 2025 - Nov 2025
  • Estimated project cost $750,000
  • Australian Government contribution $736,083
  • Local Council/Shire Moonee Valley City Council
  • State VIC

Project description

Cracked and deteriorated road pavement and kerb and channel. Poor stormwater drainage.

Replace existing road pavement and kerb and channel with new road pavement and kerb and channel. Install new underground stormwater drainage. RTR funding part of the cost for this project with the balance of cost to be from Council funds.

Total cost of proposed project is $750,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.