• Funding program Roads to Recovery Program
  • Status Under construction
  • Transport mode Road
  • Expected start/finish Oct 2025 - Dec 2025
  • Estimated project cost $344,297
  • Australian Government contribution $269,602
  • Local Council/Shire City of Salisbury
  • State SA

Project description

As part of City of Salisbury ongoing road audit process, it was identified for intervention to meet the accepted service levels. This road exhibits widespread block cracking and surface wear. The City of Salisbury will be providing the balance of funding for this project.

Complete Mill and Asphalt replacement using AC10M A5E to mitigate cracking and surface wear.

Total cost of proposed project is $344,297

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.