• Funding program Roads to Recovery Program
  • Status Under construction
  • Transport mode Road
  • Expected start/finish Nov 2025 - Jan 2026
  • Estimated project cost $422,037
  • Australian Government contribution $255,669
  • Local Council/Shire City of Swan
  • State WA

Project description

This section of Westchester Road scored an average surface condition rating of 3.82 out of 5 (with 5 being very poor) in the 2020 condition survey. Visual inspections confirm that the road requires a resurface before costly rehabilitation works are needed.

Profile off 40 mm asphalt wearing, apply 7 mm granite primer seal and lay 40 mm new Asphalt Concrete wearing.

Total cost of proposed project is $422,037

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.