• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2014 - May 2014
  • Estimated project cost $450,150
  • Australian Government contribution $22,485
  • Local Council/Shire Shire of Donnybrook Balingup
  • State WA

Project description

The subject section of Upper Capel Road is a narrow 3.8 metre wide seal and this coupled with substandard geometry (curves and crests) creates a very unsafe road environment. The seal is also approaching the end of its useful life.

Reconstruction of the subject section. Realignment of the section to improve substandard curves and earthworks to improve crests. Bitumen seal of subject section to 6.2 metres in width with minimum 1.0 metre wide unsealed shoulders either side of the seal.

Total cost of proposed project is $450,150

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.