• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2015 - Mar 2016
  • Estimated project cost $29,011
  • Australian Government contribution $29,011
  • Local Council/Shire Shire of Northam
  • State WA

Project description

Existing surface fatigued. Problems causing by ponding of water on uneven surface resulting in pavement failures and cracking of existing seal.

Surface corrections with isolated milling, kerb renewal and asphalt overlay.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.