• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2015 - Nov 2015
  • Estimated project cost $159,468
  • Australian Government contribution $159,468
  • Local Council/Shire Boulia Shire Council
  • State QLD

Project description

Road is not currently wide enough for two vehicles to pass each other. This will correct the problem on this section of road that takes a considerable amount of traffic on our Race day, Camel Races & Rodeo events.

Widen Selwyn Road by 1.5 metres on each side of the road by forming, paving and sealing an area of 2.025 Kilometres x 3 metres ie 6,075 square metres

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.