• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2016 - May 2016
  • Estimated project cost $128,888
  • Australian Government contribution $128,888
  • Local Council/Shire Sutherland Shire Council
  • State NSW

Project description

The section of road pavement has reached end of its service life and deteriorated due to road pavement base failure. Existing pavement surface severely oxidised, potholing in patches.Road pavement requires renewals of pavement base and wearing surface layer

Road rehabilitation works for 2400 sq.m pavement area . Works include 200 mm thick cement stabilised base course and 40 mm thick asphalt concrete (AC10) surface layer.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.