• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2016 - Apr 2016
  • Estimated project cost $48,000
  • Australian Government contribution $48,000
  • Local Council/Shire Mosman Municipal Council
  • State NSW

Project description

Deteriorating road surface with base failure at some sections

Mill and resheet the road with heavy patching

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.