• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2016 - Aug 2016
  • Estimated project cost $81,697
  • Australian Government contribution $81,697
  • Local Council/Shire Cobar Shire Council
  • State NSW

Project description

A small local creek is depositing large quantities of sand on causeways on the road due wet weather. These deposits make the road impassable for significant periods as the existing causeway becomes saturated.

Gravel re-sheet, form and stabilise the causeway in each location for approximately 100 metres. The stabilised formation will then be sealed.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.