• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2020 - Mar 2020
  • Estimated project cost $175,000
  • Australian Government contribution $82,595
  • Local Council/Shire Adelaide Hills Council
  • State SA

Project description

The seal on 320 m of Deviation Rd has reached the end of its useful life. Maintaining the aged seal has become a maintenance burden for Council, and the cracks are letting water through, which will compromise the pavement over time.

Profile 30 mm of existing aged and oxidised seal and reinstate with 40 mm new asphalt, using an asphalt mix which is high in recycled content.

Total cost of proposed project is $175,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.