• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2015 - Oct 2015
  • Estimated project cost $70,340
  • Australian Government contribution $28,300
  • Local Council/Shire Shire of Dumbleyung
  • State WA

Project description

Lack of gravel causing slippery surface when wet and major rutting when dry.

Clear, reform, upgrade drainage, widen resheet with gravel to 8 metre surface.

Total cost of proposed project is $70,340

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.