Bitumen surface is aged and severely cracked. That is the bitumen surface is failing, risking further failure to the road pavement.Repair surface failures and reseal road.
Asphalt surface is aged and severly cracked. That is the bitumen surface is failing, risking further failure to the road pavement.Repair surface failures and reseal road.
Superstructure deteriorated and bridge load limited.Renew bridge superstructure to meet current loading requirement.
The issue is the road is a restricted access vehicle network 4 road and the surface is only 4m wide with a large overburden of soil and vegetation encroaching on the road surface.The works will be to clear the sides of the road in 2015/2016 in readiness to widen the road to 8m to allow vehicles travelling in opposite directions to pass each other in 2016 / 2017.
During the works required to complete the grain transport network, heavy vechiles were required to use Smith road to access gravel pits. As a result the gravel sheet surface of the road was worn away.The works will be to resheet the gravel surface of the road.
Following the contrcution of the new section of Kellerberrin Shakelton Road, the old section was closed. At that time Kwolyin East Road ended a 'T' Junction with the closed road section.The works are designed to realign the intersection area to join the two sections of Kwolyin East Road, removing the sharp angled bends.
During the works required to complete the grain transport network, heavy vehicles were required to use Fisher West Road. As a result the gravel sheet surface of the road was worn away.The works will be to re-sheet the gravel surface of the road.
The issue is the road is a restricted access vehicle network 4 road and the surface is only 4m wide with a large overburden of soil and vegetation encroaching on the road surface.The works will be to clear the sides of the road and widen the road to 8m to allow vehicles travelling in opposite directions to pass each other.The project includes sealing and wet mixing.
The issue is the road is a restricted access vehicle network 4 road and the surface is only 4m wide with a large overburden of soil and vegetation encroaching on the road surface.The works will be to clear the sides of the road and widen the road to 8m to allow vehicles travelling in opposite directions to pass each other.Total cost of proposed project is $485,931
The existing surface and pavement is showing signs of distress and is near the end of its useful life - current condition of road not providing adequate level of service.Propose to resurface road for a length of 900m and a width of 5.8m.Total cost of proposed project is $513,634