Existing gravel road is no longer of an appropriate standard given the significant increase in traffic volume.Construction of road pavement and sealing.
The existing gravel pavement is prone to variable conditions including corrugations and potholes, requiring regular maintenance to rectify defects, and dust can be an issue within the cemetery.Drainage maintenance, reshape road formation and verges; supply, spread, compact and trim natural gravel pavement material to improve pavement strength, and apply a two-coat bituminous surfacing to the roads.
The road is very rough, with pavement and some sections of kerb and gutter in poor condition; and has poor cross-sectional shape and mid-block traffic arrangements not conducive to safety.Replace sections of damaged kerb and gutter, construct mid-block roundabout at the Sommerlad Lane intersection, and rehabilitate road pavement by ripping the existing surface, chemical and/or mechanical stabilisation, and bituminous surfacing.
The road is very rough, with pavement and some sections of kerb and gutter in poor condition.Replace sections of damaged kerb and gutter, and rehabilitate road pavement by ripping the existing surface, chemical and/or mechanical stabilisation, and bituminous surfacing.
The road is in very poor condition with a very rough surface leading up to a popular tourist attraction at the Australian Standing Stones.Rehabilitate the road pavement by ripping the existing surface, applying chemical and/or mechanical stabilisation to the gravel pavement, and bituminous surfacing.
Existing gravel road is no longer of adequate standard due to significant residential growth in the area.Road pavement is to be constructed and road sealed.
Gravel loss over time and drainage problems, leading to rough road surface and excessive maintenance of this section of road to meet service levels.Perform drainage maintenance; vegetation control; supply, spread, compact and trim natural gravel pavement material to improve pavement strength and restore an appropriate cross section to the road.
Timber bridge deck is in poor condition.Replace timber deck with new concrete deck.Total cost of proposed project is $383,000
Gravel loss over time and drainage problems, leading to rough road surface and excessive maintenance of this section of road to meet service levels.Perform drainage maintenance; vegetation control; supply, spread, compact and trim natural gravel pavement material to improve pavement strength and restore an appropriate cross section to the road.
Gravel loss over time and drainage problems, leading to rough road surface and excessive maintenance of this section of road to meet service levels.Perform drainage maintenance; vegetation control; supply, spread, compact and trim natural gravel pavement material to improve pavement strength and restore an appropriate cross section to the road.